Hooker Creek: Projects

Page:
http://hookercreek.net/ready-mix-concrete/profiles/
Date:
07-31-2010
Phone:
541-389-0981

Construction Materials - HOOKER CREEK

 

Franklin Crossing

Overview:
> Named top Commercial Project in Central Oregon in 2005.
> Finalist for Excellence in Concrete Award in both 2007 and 2008.
> First underground parking structure in Bend.

Project Details

Located at the heavily traveled intersection of Franklin and Bond Streets in downtown Bend, Oregon, Franklin Crossing is a five-level, mixed use development that combines beautiful form with sophisticated function.  The 69-foot structure encompasses approximately 131,600 square feet that includes the first underground parking facility in Central Oregon.  This unique structure allows a person to live at the most prominent address in downtown Bend, shop at some of the trendiest stores and work in a space that is much more than just an office, all under one roof.  Hooker Creek delivered over 800 truckloads of concrete for this project during the 2 years of construction.  We also supplied the Insulating Concrete Forms (ICF's) that were utilized in the consruction of the Condo's on the top floor.  Insulating Concrete Forms were used because of their sound deadening and energy saving qualities.  Construction on this amazing structure began in 2004 and was completed in late 2006.

St. Francis of Assisi Catholic Church - Bend, Oregon

Overview:
> Seats 800 people
> Standing room for an additional 200 people.
> Project completed in late 2009
> General Contractor - Kirby Nagelhout Construction
> Hooker Creek Companies, LLC - Concrete Supplier

Project Details

    The new St. Francis of Assisi Catholic Church in Bend, Oregon is located adjacent to St. Francis School on the east side of town.  The main sancturary has 48 ft cast in place concrete columns on the tall side with a sloping roof down to 26 ft on the low side that is supported by cast in place concrete columns.  The main roof structure is held up by two 135 ft beams that sit atop the cast in place concrete columns.  There are also cast in place concrete beams at the low end that support the roof structure as well as large glass window assemblies.
    There are 30 concrete columns in all with nine different shapes to them.  They range in height from 12 ft to 48 ft tall.  There is not one column that was designed to be square.  There are basic rectangular columns, trapezoid shaped columns and columns that have seven different faces on them and as thick as 5 ft through.  Some of the columns have as many as seven window openings in them that had to be blocked out during the pouring of the columns.  These window openings had no trim; therefore they had to be exact when the columns were poured.
    In addition to the concrete columns, there was approximately 320 ft of cast in place concrete beams that were poured.  Once again the concrete beams were irregular shaped.  Some were rectangular, some were poured at angles to match the roof pitch, and some were tapered with sloped tops for the roof framing to sit on.
    This is a one of a kind building.  There is hardly a 90 degree building project in the entire project.  Even the tops of the concrete columns were poured at angles to match the roof slope.  All of the finished floors in the church, except for 1,000 sq. ft. of tile in the bathrooms, is exposed aggregate concrete.  Installing the floors was a huge challenge for those working on the project as they built the entire structure and then poured the floors at the finish stage of the project.
    The end result is a beautiful, modern structure that preserves some of the history of the old catholic church located in downtown Bend. 

Central Oregon Community College Campus Center

Overview:
> Over 550 yards of concrete
> Over 3,000 blocks of Reward ICF
> One of the largest commercial ICF projects in Central OR

Project Details

Construction on the new Campus Center at Central Oregon Community College began in early June of this year.  The 30,000 foot building will utilize approximately 3,000 block of Reward Wall Systems Insulating Concrete Forms and approximately 550 yards of concrete.  
     This is one of the largest commercial projects in Central Oregon to utilize the ICF's.  It is expected that by utilizing ICF's in the construction of this building, the college will see a substantial savings on their energy bill.  The project is expected to be completed in early 2009 with the grand opening slated for March of 2009.

Deer Ridge Correctional Institute

Overview:
> Approximately 24,000 ton of asphalt
> 12,000 yards of concrete
> Top 20 construction projects in Central Oregon

Project Details

Deer Ridge Correctional Institute is a minimum and medium security men's prison located on approximately 200 acres three miles east of Madras.  The estimated square footage for the minimum security area is 185,000 feet and the medium security area encompasses approximately 400,000 square feet.  When full there will be approximately 860 beds in the minimum security area and 1,240 medium security beds.  The total cost of the project is estimated to be $193 million.  Hooker Creek was involved in this project in various capacities. 

Asphalt and Paving:  Hooker Creek Asphalt and Paving was contracted for the paving work for all phases of this multi faceted project.  This includes Ashwood road leading to the prison.  Approximately 24,000 ton of asphalt was needed to complete all phases of the project.  Value of the paving portion of the project was approximately $1.6 million not including all of the Aggregate base sand and gravel.
Paving Project Manager

Redmond 5th Street Reconstruction Project

Overview:
> Total Value of Project is Approximately $3.3 Million
> ODOT Job Funded by Stimulus Dollars
> Work Began in August 2009
> Scheduled Completion Date is June of 2010

Project Details

Important Information Regarding the Redmond 5th Street Reconstruction Project - Updated Wednesday, June 2, 2010.

    As we enter the final weeks of work on the Redmond 5th Street Reconstruction Project, we would like to let business owners along 5th Street and those who must use 5th Street on a regular basis know that over the next couple of weeks, there will be times when business access and side street access will be closed or severely limited.  We strongly encourage those who normally travel through downtown Redmond using 5th Street to use alternate routes on June 11 and 14 and then during the week of June 21 - 25.
   Beginning on Monday, June 7 our crews will be working north of the Y to Jackpine.  During this time the let turn lane onto Jackpine will be closed.
    Hooker Creek paving crews are scheduled to lay the base lift of asphalt on the west lane of 5th STreet from Black Butte to Jackpine on Friday, June 11 and Monday June 14.  One these days business access along the west side of 5th Street between Black Butte and Jackpine will be limited.
    From Tuesday, June 15 - Friday, June 18 members of our team will be installing pavers along the west side of 5th Street, installing signs, working on clean up along 5th Street and completing the final prep work for laying the top lift of pavement.  There will be normal access to 5th Street and all side streets and businesses at this time.
    During the week of June 21 - 25 Hooker Creek crews will be on the road from 5 PM - 7 AM as they lay the final lift of asphalt on both the east and west lanes of 5th STreet from Glacier to Quince.  During this week, 5th Street business acess will be closed from 5 PM - 7 AM and there will only be partial access during daytime hours.  

----------------------------------------------------------------------
 Hooker Creek Companies, LLC is pleased to be the general contractor for the Redmond 5th Street Reconstruction Project.  This very much anticipated project is an ODOT project funded by stimulus dollars.
    The full scope of this multi faceted project includes removing and replacing all of the old asphalt on 5th Street between Glacier and Jackpine and the removal and replacement of much of the curb and sidewalk along both sides of this same section of 5th Street.  The  project also included replacing the old water main that, in some places, had been there since before World War II.  
    Hooker Creek crews began working on the project in August of 2009.   Our anticipated completion date is in June of 2010.  
         For detailed updates on this project, please check out our weekly updates in the news section of this web site.